Over 600 pieces of equipment were shipped in from all over the world for the Shell Tiger AO4 project. Much of the equipment was received and transported by Turner Industries specialized transportation group. The transportations were preceded by over a thousand engineering hours, and some required specialized super heavy hauling permits, soil, paving and bride analysis. Some vessels were shipped via barges on the Mississippi River and required coordination with the US Army Corps of Engineers. The project cost $1 billion to complete.

  • Turner Industries
  • Geismar, LA
  • 2018